What is an Extension of Time Notice?
Construction contracts generally allow the construction period to be extended where there is a delay that is outside the contactor’s control. An Extension of Time (EOT) Notice is a provision in a construction contract that allows the contractor to make a formal request for an additional time period to complete the project beyond the originally agreed-upon completion date.
This request (EOT Notice) is usually made due to circumstances that caused delays to the project outside the contactor’s control, such as unexpected weather conditions, changes to the scope of work and delays in the delivery of goods.
Delays That Justify an Extension of Time
– Variations of the contract scope of work requested by the client.
– Adverse weather conditions that affect the ability to work.
– Failure of or delay by the client to provide information requested by the contractor.
– A delay in the contractor gaining possession of the site.
– Force majeure (e.g. an epidemic, industrial actions, civil commotion, acts of God). COVID 19 was an example.
– Delays in the supply of materials outside the control of the contractor.
– Changes in statutory requirements or delays in receiving permissions outside the control of the contractor.
Submitting a Successful Extension of Time Claim
Submitting a claim for delays or disruptions to the work schedule can be a complicated process. The quality of available records and the information provided are vital to ensure that claim is successful. The claim should establish the cause of the delay and the extent of the disruption directly caused by such delay.
It is important for the contractor to have an accurate baseline programme before work begins. The programme should be updated and revised continually to reflect the changing project conditions. This will allow the contractor to establish the impact that a delay is likely to have on their ability to complete the activities on time, and make it easier to prepare the Extension of Time claim.
Events that cause or likely to cause delays should be recorded by the contractor, and these could include:
– When the event occurred and why it occurred.
– The tasks affected and the reasons why they were affected.
– The additional resources that it required.
– A list of the affected activities.
– Any other activities that had to be carried out as a result.
– Supporting documents, including sketches, photographs and plans.
– Details of actions taken by the contractor to minimise delays.
– Proposed recovery plan.
Effective Management of Extension of Time (EOT)
In the dynamic realm of construction projects, unforeseen circumstances often arise, leading to delays and disruptions. Managing extension of time requests is pivotal in ensuring that projects stay on track and are completed successfully.
This section explores the importance of effectively managing extension of time requests in construction projects and highlights key strategies and benefits of a structured approach.
Managing extension of time requests begins with a prompt evaluation of the circumstances causing the delay. Project teams should establish a clear process for submitting and reviewing requests. Accurate and detailed documentation of the events and their impact on the project timeline is essential. This documentation provides a comprehensive basis for evaluating the legitimacy of the request and helps prevent disputes.
To effectively manage extension of time requests, project managers must conduct a thorough analysis of the causes of the delay. This includes reviewing project schedules, contracts, and relevant documentation to determine the responsibility for the delay. Identifying the root causes enables project teams to address the issues appropriately and allocate resources accordingly. It may also help in minimizing the occurrence of similar delays in the future.
Effective communication and collaboration among project stakeholders are crucial when managing extension of time requests. Regular meetings, progress updates, and clear channels of communication ensure that all parties are aware of the delay and its impact on the project. Collaboration between contractors, sub-contractors, consultants, and project teams fosters a proactive approach to resolving delays and minimizing their impact on the overall timeline.
Managing extension of time requests requires a fair and transparent evaluation process. Project managers should establish clear criteria for assessing the validity of a request, considering factors such as the responsibility for the delay, the reasonableness of the request, and the impact on the project schedule. A structured evaluation process helps ensure consistent decision-making and minimizes the potential for disputes.
Managing extension of time requests involves proactive risk management. Project teams should identify potential risks and factors that might lead to delays during the project planning phase. By incorporating contingency plans and proactive risk mitigation strategies into the project schedule, project managers can minimize the need for extension of time requests. This approach helps maintain project momentum and reduces the overall impact of delays.
Managing extension of time requests requires a thorough understanding of the contractual obligations and provisions related to time extensions. Project managers should be familiar with the specific clauses and conditions outlined in the contract, including notice requirements, time limits for submitting requests, and the process for granting extensions. Compliance with contractual obligations helps protect the project’s interests and ensures a fair and equitable resolution.
Articles and References
Extension of Time in Construction Contracts
https://www.contractsspecialist.com.au/articles/extension-of-time-contracts/
Extension of Time In Construction Projects
https://www.researchgate.net/publication/363100485_Extension_of_Time_In_Construction_Projects
Extension of Time (EoT) Considerations in Construction
https://iopscience.iop.org/article/10.1088/1757-899X/1101/1/012030/meta
Guideline for preparing comprehensive extension of time (EoT) claim
https://www.sciencedirect.com/science/article/pii/S1687404814000091
Extension of Time in Construction Contracts
https://www.lexology.com/library/detail.aspx?g=31fe34a1-29bc-4521-94e1-51200b003027
Extension of Time in Construction Contracts – JCT
A Practical Approach to Managing Extension of Time Claims
http://www5.austlii.edu.au/au/journals/ANZRIArbMedr/2003/22.pdf
Concurrent delay
https://www.pwc.com.au/legal/assets/investing-in-infrastructure/iif-24-concurrent-delay-feb16-3.pdf
EXTENSION OF TIME (EoT) CLAIMS SUBSTANTIATION AND ASSOCIATED ISSUES
What Are a Contractor’s Rights to an Extension of Time?
https://legalvision.com.au/extension-of-time-rights-of-the-contractor/
Critical Path Method (CPM) is a defining resource for the construction industry. First developed in the late 1950s, the critical path method has been utilised in a variety of project development projects including engineering, aerospace and plant maintenance. CPM has rapidly become an essential staple for construction projects today, but many business owners are intimidated from what is perceived as a complex process.
The value of As Built drawings is often underrated, especially their importance for the efficient management of the project after construction has been completed. This article takes a brief look at As Built drawings; what they are, how they are created and why they are important.
The customary monthly clients meeting is a time when you have the chance to give your clients progress updates about their project and provide them with a monthly report. Your monthly report says a lot about your professionalism and should not be rushed or overlooked. It is an ideal way to instill confidence in your clients about your company’s ability to communicate, and to demonstrate that you have a solid understanding of their project and their priorities.
© 2021 Tenderfield Pty Ltd – All rights reserved.